Contract award
Contents |
[edit] Introduction
The term ‘contract award’ refers to the process of formally notifying a tenderer that they have been selected as the supplier for a particular contract.
Before a contract can be awarded, a selection process is likely to have been undertaken which might involve:
- Adverts placed, or recommendations received for a long list of potential tenderers.
- A pre-qualification process.
- Identification of a short list to be invited to tender.
- An invitation to tender.
- Tender receipt.
- Interview.
- Selection of preferred tenderer(s).
- Negotiation.
- Contract award.
- Contract engrossment (printing) and execution (signing as a deed or as a simple contract).
[edit] Selection criteria
There are a number of different bases upon which a contract can be awarded:
[edit] Lowest price
In this simple method, the lowest priced tender (or best price) wins the contract. However, following this method excludes other elements of the tender, such as relevant experience, being taken into consideration when awarding the contract and does not always result in best long-term value for the client. Low prices can produce low quality, or result in claims and conflict between the client and the supplier.
[edit] Most economically advantageous tender (MEAT)
This method allows for factors other than, or in addition to, the price to be taken into consideration, such as quality, experience, competence, capability, capacity, estimated time for completion, life cycle costs, and so on. If this method of awarding is to be used, it should be set out in the tender documents, along with the system of weighting that will be applied to each of the selection criteria.
For more information, see Most Economically Advantageous Tender (MEAT).
[edit] Mean value
This method awards the contract to the bid that is closest to the mean value of the proposals. This is commonly adopted where numerous proposals are expected, but can leave suppliers uncertain where to pitch their bid.
[edit] Exclusion of the extremes
This method is used to take away the bids that deviate most, lowest and highest, before then proceeding with one of the three methods above.
[edit] Contract award procedure
Once the successful tenderer has been selected a period of negotiation will begin. A reserve tenderer may be retained in the event that negotiations with the preferred tenderer are unsuccessful.
A tender report may then be prepared providing a brief history of the tendering process and an analysis of each tender submission and any subsequent negotiations and concluding with a recommendation.
All tenderers should be informed of the decision to award the contract to a particular tenderer.
If OJEU procedures are being followed, it may be necessary to publish a formal contract award notice once the successful tenderer has been selected. A ‘standstill period’ may then be required. This is a pause of at least 10 calendar days between the decision being notified to all tenderers and the final contract conclusion. This allows for suppliers to challenge the decision.
The contract administrator (or sometimes the cost consultant) then collates the contract documents and arranges for the printing (engrossment) and execution of two copies, one for the client and one for the supplier. Alternatively, the client might retain one executed contract, with certified copies being issued to the supplier, this can avoid potential errors in preparing two contracts for execution. The supplier may be required to provide a performance bond, warranties, evidence of insurance cover, and so on.
Contract award and contract execution may not necessarily happen at the same time. In fact it is relatively common (although not advisable) for contracts to remain unsigned until well after work has begun.
Contracts may be executed under seal (signed by the parties, witnessed and most importantly made clear that they are executed as a deed) or under hand (a 'simple contract' that is just signed by the parties). See Contracts under seal v under hand for more information.
[edit] Award notice
An award notice is a public notice that may be required under OJEU procurement rules that notifies interested parties of a contract award and sets out information about the process that led to the award.
[edit] Related articles on Designing Buildings
- Back to back provisions in construction contacts.
- Best value procurement.
- Bid evaluation.
- Compliant bid.
- Contracts under seal v under hand.
- Construction contract.
- Contract conditions.
- Contract documents.
- Contract negotiation.
- Engrossment.
- ESignatures.
- Guaranteed maximum price.
- Letter of award.
- Most Economically Advantageous Tender (MEAT).
- Negotiated contract.
- OJEU procurement procedures.
- Procurement route.
- Record keeping.
- Sub-contract.
- Tender documentation.
- Tender processes.
Featured articles and news
About the 5 Percent Club and its members
The 5% Club; a dynamic movement of employers committed to building and developing the workforce.
New Homes in New Ways at the Building Centre
Accelerating the supply of new homes with MMC.
Quality Planning for Micro and Small to Medium Sized Enterprises
A CIOB Academy Technical Information sheet.
A briefing on fall protection systems for designers
A legal requirement and an ethical must.
CIOB Ireland launches manifesto for 2024 General Election
A vision for a sustainable, high-quality built environment that benefits all members of society.
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.